Milestones and dependencies

Finish the complete team project by December 30, 2026. Dates here are team targets in Beijing time, with required work taking priority over optional scope.

Calendar

gantt
    title Team delivery plan - 2026
    dateFormat YYYY-MM-DD
    axisFormat %b %d
    tickInterval 1week
    section M1 foundation
    Agree shared contracts and examples :2026-11-23, 4d
    Page and record storage             :2026-11-25, 10d
    CLI parser catalog and basic SQL    :2026-11-25, 10d
    M1 complete - Dec 6   :milestone, 2026-12-06, 0d
    section M2 required engine
    B+ tree and index maintenance       :2026-12-07, 9d
    DML joins keys ALTER and import     :2026-12-07, 10d
    Full suite and benchmark            :2026-12-17, 3d
    M2 complete - Dec 20              :milestone, 2026-12-20, 0d
    section M3 delivery
    Select and finish optional scope    :2026-12-21, 5d
    Report evidence and demo rehearsal  :2026-12-23, 7d
    M3 release and report - Dec 30:milestone, 2026-12-30, 0d

Dependency map

flowchart TB
    C[CORE-001 to 003: agree interfaces] --> S[STORE-001 to 004: files, cache and rows]
    C --> P[PARSE-001, CLI, CAT-001]
    S --> BASIC[DB and TABLE commands, INSERT and SELECT]
    P --> BASIC
    BASIC --> M1{M1: restart and system/table gate}
    M1 --> TREE[INDEX-001 to 006: B+ tree and maintenance]
    M1 --> SQL[WHERE, UPDATE, DELETE and joins]
    TREE --> KEYS[KEY and ALTER specifications]
    SQL --> KEYS
    TREE --> IMPORT[SQL and CLI bulk import]
    KEYS --> M2{M2: full required suite and benchmarks}
    IMPORT --> M2
    M2 --> CHOOSE[Select optional scope]
    CHOOSE --> FINAL[Report, demo and reviewed release]
    FINAL --> M3{M3: December 30 complete}

M1: a usable persistent database

By December 6, a user can create a database, select it, define a typed table, insert rows and query selected columns. SHOW, DESC and DROP work. Table definitions and row values are written to system files. A new process can reopen them and return the same results. Both teammates can demonstrate this on Linux.

The scored checkpoint is system + table, 12 raw points. That checkpoint alone does not prove INSERT/SELECT persistence; TEST-001 separately verifies those behaviors. The interface review is due at the start of M1, even though all M1 issues carry the December 6 milestone deadline.

M2: the complete required engine

By December 20, all required commands work together: filtering, updates/deletes, two-table joins, eight-table import, single/composite primary and foreign keys, adding/dropping constraints, multiple explicit indexes, and maintained B+ tree access. Run the complete dependency-aware required suite from clean initialization and expect 62 raw points. Then run official course CI and retain evidence.

Benchmark only correct results. Include memory and page-read measurements so a faster query is not achieved by loading every table into RAM.

M3: a finished submission package

By December 30, selected extras are implemented and tested, the report is complete, both teammates can explain and demonstrate their code, and a reviewed release is on master with the tested commit recorded. Reserve the last days for integration and evidence; optional issues can stay unselected.

The published acceptance date is January 17, 2027, subject to later course announcements. The individual product survey is separate from this team plan. Check its own announcement for the current deadline and hand-in route.

DBS 005 · Specification v1 · Team review required for proposed interfaces.
Engine behavior is planned; implementation progress lives in GitLab.